Site Opening Permit (Sub-Decree 224 on Construction Permit)

Construction Site Opening Permit (Sub-Decree 224 On Construction Permit)

  1. Site opening permit is needed before starting any construction activity.
  2. Starting date of new construction work is when there are any progresses of excavation or piling work.
  3. In case the competent authority does not complete on construction permit application in the duration determined in this sub-decree, the applicant can proceed to request for construction opening permit from that expired date. 
  4. Construction site opening permit will be expired in 1 year after issued date if there isn’t any construction activity start.


[Sub-Decree 224 On Construction Permit]