Construction Permit in Cambodia (Sub-Decree 224 On Construction Permit)
- The authority of Minister of MLMUPC:
- Total building floor area > 3000 sq.m
- Floors of building ≥ 11 floors
- Basement height ≥ 5m
- Retaining wall height ≥ 5m
- The authority of Provincial governor of board governor:
- Total building floor area ≤ 3000 sq.m
- Floors of building < 11 floors
- Basement height < 5m
- Retaining wall height < 5m
- The authority of District board of governor
- Total building floor area ≤ 500 sq.m
- Floors of building ≤ 4 floors without basement
- Brick or concrete wall with height ≤ 3m
- The construction permit will be expired in 1 year after the issued date in case the construction activity has not started.
- In case the owner receives the construction site opening permit, the start date of construction permit will be changed to the issued date of the opening permit.
- The construction in real estate development project can be allowed to construct by phases following the planning shown in land development permit.
- The application for a construction permit by subdivision into small project of housing development project for a business purpose in which a single building owner has the same land owner and is on the same plot is prohibited.
- Projects for the construction of flats or housing for business purposes located on the same plot of land must have a construction site opening permit before allowing title subdivision.