Guidelines for Repairing Defects of Roads by General Directorate of Techniques Road Infrastructure Department MPWT 2017

Guidelines for Repairing Defects of Roads by General Directorate of Techniques Road Infrastructure Department MPWT 2017 


Table of Contents
1 1100 Pothole repair- Asphalt Concrete (AC) by Plant Hot Mix (m2)
2 1101 Pothole repair- Asphalt Concrete (AC) by Site Mix (m2)
3 1131 Crack filling 1 layer 12mm aggregate with CRS-2 (m2)
4 1132 Crack filling 2 layers 19mm then 12mm aggregate with CRS-2 (m2)
5 1140 Repaired paved shoulders (m2)
6 1150 Shape correction (Ruts/Settlement) (m2) 
7 1161 Pothole repair- mixed stone based- DBST (m2) 
8 1162 Pothole repair-cement mixed based-DBST (m2)
9 1163 Pothole repair-mixed gravel CRS2 & cement based – DBST (m2) 
10 1164 Pothole repair – Excel Patch (m2) 
11 1160-3 Temporary road restore to facilitate traffic- laterite (m3) 
12 1160-C3 Temporary road restore to facilitate traffic- mixed gravel (m3)
13 1180 Reinforced concrete road – thickness 200mm (m2) 
14 1200 Grading Shoulders (km)
15 1201 Adding laterite to road shoulder (m3) 
16 1250 Grading Laterite (km) 
17 1260 Heavy grading laterite road (km)
18 2100 Channel cleaning by labour (m)
19 2110 Channel Cleaning by machine (m)
20 2150 Excavate channels by machine (m)
21 4800 Clearing rock falling (m3)
22 3100 Cleaning culvert transversal (nos.)
23 3110 Cleaning culvert longitudinal (m)
24 3130 Repair culvert transversal (nos.)
25 3141 Repair pipe culvert longitudinal (m)
26 3142 Repair box culvert longitudinal (concrete) (m)
27 3150 Install pipe culvert (m)
28 3200 Minor Bridge Repair (person.hour) 
29 4150 Vegetation control (Shrub, Plant and Tree) (km) 
30 4200 Sand bag work -slope protection (bag)
31 4400 Grass planting on the slope (m2) 
32 4500 Adding soil to the slope (m3)
33 4610 Access road (public to national road) by AC (m2)
34 4620 Access road (public to national road) by DBST (m2)
35 4630 Access road (public to national road) by macadam (m2) 
36 4700 Dragon hole filling (m3)
37 5100 Traffic lanes painting (Thermoplastic) (m) 
38 5200 Clean and paint traffic sign (nos.)
39 5230 Traffic sign repair (nos.)
40 5250 New traffic sign installation (nos.)
41 6100 Cleaning and painting safety pole (nos.)
42 6150 Safety poles installation (nos.)
43 7100 Cleaning & painting kilometer post (nos.)
44 7130 Repairing kilometers post (nos.)
45 7150 Kilometer post installation (nos.)
46 7200 Replacing safety guardrail (steel) (m)